Demurrage –  CFR/CIF Sale – the buyers liable to sellers for delay caused by port authorities after commencement of discharge 

Facts

Cement was loaded in China  to be discharged at Diego Suarez, Madagascar.

 The CFR sale contained laytime and demurrage provisions – buyers’ liability.  Sellers were the charterers of the vessel.

 After commencement of discharge, port authorities required the vessel to give up its berth to a priority tanker causing delay of about two days.  

 Excluding the period of delay, buyers completed the discharge within the laytime available.  

 The most interesting (and probably be the most important) issue to be decided between the buyers and the sellers was whether laytime continued to run during the period of the delay caused by the port authorities.  

 Findings

This content is restricted to site members. If you are an existing user, please login. New users may register below.

Existing Users Log In
   
New User Registration
Please indicate that you agree to the Terms of Service *
captcha
*Required field
Charter Party Casebook