Repudiation – Premature re-delivery by charterers – owners held entitled to refuse such
The facts
The vessel was chartered on an amended NYPE form for 59 – 61 months. There was an express warranty that the vessel would not be re-delivered before the minimum of 59 months.
Charterers gave notice that the vessel would be re-delivered 94 days prematurely.
Owners commenced arbitration before re-delivery took place requesting a partial final award that they were entitled to refuse early re-delivery and to hold the charterers liable for hire for the remainder of the minimum period.
Findings This content is restricted to site members. If you are an existing user, please login. New users may register below.